Role definition

The Release Manager will be is a volunteer position, much like WG chairs, that will be is staffed by contributors from member companies. The responsibility of a Release Manager is to coordinate the common tasks of each release that span across working groups, ensuring that the required release tasks are being performed on schedule and escalating any potential problems to the TSC and relevant working groups as early as possible.

...

Because the dates of each release will vary, the times here are given as time before (-) or after (+) a given release.

Date

Task

T - 7 months

New Release Manager is selected and introduces themselves to the project.

T - 6.5 months

Request version bump on all EdgeX Foundry projects, verify that they have been merged.

T - 6 months

TSC Face to Face meeting

T - 6 months

Collect list of features & issues from each working group that they plan on completing for the release (should be available after the TSC face to face meeting)

T - 6 months

Create new “Release Schedule” wiki page, fill in dates for freezes, branching and final release (should be known after the TC face to face)

T - 5 months

Request new Github milestone for the release, assign targeted issues to it

T - 5 weeks

Send email reminder about upcoming feature freeze on the master branch

T - 4 weeks

Send email announcing master branch feature freeze, request freeze exceptions for any late-landing features

T - 3 weeks

Send email reminder about upcoming code freeze on the master branch

T - 2 weeks

Send email announcing master branch code freeze, request that the Linux Foundation release engineer create a release branch from master

T - 1 week

Send email announcing the release branch availability, lift the freeze on the master branch

T - 1 week

Verify that developers/devops have configured CI to build staging artifacts (docker images, snaps) from the new release branch.

T - 3 days

Generate Release Notes document (using release metrics script and providing highlights from the release) and publish it to the wiki.

T - 2 days

Provide release information to marketing and LF PR for release announcement

T - 1 day

Coordinate with WG chairs to identify which staging artifacts will be the official release, email the LF Release Engineer requesting that the release be made by providing them the Jenkins job for the desired artifact.

T = 0

Verify that stable release images have been published to Docker Hub

T = 0

Verify that stable snap package has been published to the Snap store

T = 0

Verify that the release announcement has gone out with link to Release Notes

T + 1 week

Send email announcing x.1 target release date and targeted features/bug fixes

T + 2 weeks

Send email reminder about upcoming point release freeze

T + 3 weeks

Send email announcing release branch code freeze

T + 4 weeks

Verify that stable release artifacts (docker images, snaps) of the point release have been published